2005

January
2005
New Work-For-The-Dole Supervisor appointed. - Mr Mal Mclure was appointed to the position of Work-For-The-Dole Supervisor. Mal replaced Wally Beeby who has been supervisor during the previous two years. Work-For-The-Dole schemes had by then operated on the VGR for three years, the WFTD contribution to the Muckleford - Castlemaine Project was outstanding, and under Wally's leadership had maintained and lifted the standard of the track in the Maldon - Muckleford Section also.
 

10th
January
2005
Y 127 arrives at Castlemaine - Seven-O-Seven Operations Inc. Y 127 arrives at Castlemaine. The loco is on lease to the VGR as back-up motive power for those occasions when a steam loco is unavailable, including Total Fire Ban days. At the time of Y 127's arrival, only K160 is in traffic, with J 549's return awaiting the fitting of new tyres. The transfer from Melbourne was hastened by the 17th Jan closure date for the main line between Sunbury and Bendigo as part of the Fast Train works. Y 127 was transferred from Melbourne on a special SSR train consisting of three T class locomotives (377,363,369) as motive power, with the load of S300, B65, B80 & S311 (these un-powered), sleeper and ballast wagons, with Y127 at the rear. The B's & S's were being transferred to Bendigo for repair works. Y 127 was driven under its own power to Thompson's Siding where it was stabled pending transfer to Maldon. See 'Y 127' photographs.
 

14th
January
2005
Y 127 transferred to Maldon - the Y was driven from Thompson's Foundry Siding into the VGR yard. The move was conducted under the supervision of a Pacific National Block Inspector as the spiked cross-over to the Maryborough Line had to be opened for the movement. Later the Y was attached to first Maldon train of the day. See 'Y 127' photographs.
 

17th
January
2005
Sunbury - Bendigo Line Closure. The section of the main Bendigo line from Sunbury to Bendigo closes for works in relation to the Regional Fast Rail Project. Buses replace passenger rail services.
 

19th
January
2005
Y 127 works its first VGR trains. With a Total Fire Ban in force, the Y hauled the two Maldon - Castlemaine return trips of the day.
 

19th
January
2005
Lions Club of Castlemaine donates station seats to VGR To coincide with the opening into Castlemaine the Lions Club of Castlemaine presented the VGR with three Station Bench Seats. These excellent units have reproduction 'VR' insignia cast ends with sturdy timbers for the seats and backs. A big Thank You to the Castlemaine Lions, a valued and lasting addition to the Railway Atmosphere at VGR Castlemaine. See Photograph
 

20th
March
2005
Official Opening of VGR to Castlemaine. Special train conveyed guests from Maldon to Castlemaine for speeches and the unveiling of a plaque at Castlemaine Station to mark the opening of the Muckleford to Castlemaine section of the VGR.
 

23rd - 29th
May
2005
Realignment of the VGR track at Castlemaine undertaken by contractors in conjunction with works for the Regional Fast Rail Project. Associated work included relocation of the turnout in the Maryborough line and the turnout in the main line loop (old down line) to form the crossover with the Maryborough Line, and re alignment of the fast and loop tracks. The VGR track between the catch points and No 3 Platform was realigned, including the turnout with No 4 road. Along this section the signal pull wire (Post 5 Signal 50) and the catch point & lock (65 & 64) rodding was relocated. Post 4 (with signals 87, 86 and 74) was moved a short distance to clear the new track position. See photographs