Victorian Goldfields Railway

2001
Previous    Index    Next
2001
16th February
State (Victorian) Government allocates $100,000 for restoration works at Castlemaine Station & Yard. Aim for west yard to be available to trains from main rail system by end 2001.  
2001
March
Castlemaine - Work commences on the track and station building. Trackwork to complete connection with Maryborough Line, refurbish Nos 3 (platform) & 4 (run-around) Roads, portion of No 3 siding as headshunt and construct 250 metre siding to turntable.  
2001
March
Castlemaine - A good deal of site 'cleaning-up' to enable access and storage of materials, particularly at down end of yard undertaken.  
2001
18th May
Castlemaine Yard - Upgrade work to VGR security compound at the down end of the yard completed by contractor.  
2001
24th May
Castlemaine Yard- Road Vehicle access from down end of the yard to the turntable area completed.  
2001
25th May
Federal Government allocates $550,000 for Muckleford-Castlemaine Restoration.  
2001
21st June
State Government allocates $915,000 for Muckleford - Castlemaine Restoration. Trains to be operating Maldon - Castlemaine by end of 2003.  
2001
July
Recovery of Bridge Materials from former Natimuk Line - Work commenced on 14th July dismantling three timber bridges on the former Natimuk Line at Quantong. In just over two weeks work the small group of workers stripped all timbers, except piles, from the three bridges, recovering beams, cross-heads, decking and steel work (washers, irons, etc.) for reuse on VGR bridges. Transport of the recovered materials to Castlemaine was completed by the 3rd August.  
2001
August
Castlemaine Station - Spouting, downpipe work along No 3 platform and patching work on main roof completed.  
2001
August
Workers for the Bridge Repair Gang are appointed and commence work, restoration of Winters Flat Bridge commences. Restoration of the five timber bridges in the Castlemaine - Muckleford section is anticipated to take one year.  
2001
21st September
Castlemaine Station- Asphalt repairs / works to surface of platform 3 completed. Contract let by VicTrack, Contractor Boral Asphalt, VGR representative present during works.  
2001
28th September
Castlemaine Yard- During the week ending 28th September the installation of the catch points within the access road achieved.  
2001
November
Track - Concentrated effort by VGR crews sees existing track between Farmer's Bridge and Sawmill Road (Prison Farm) Bridge dismantled.  
2001
1st December
Track Relaying - First length of new track is laid, UP side of Farmer's Bridge.  