Victorian Goldfields Railway
1982
|
| 1982 |
February |
Meeting with Ministry for Transport to discuss progress. |
RSA76-86 |
| 1982 |
June |
8 Carriages moved from Melbourne to Castlemaine by Vic Rail. Restoration work commences. |
RSA76-86 |
| 1982 |
October |
Inspection of trestles and track by Vic Rail Gang.
Maldon Council commences restoration of Station building.
7 members donate cost of carriages.
Castlemaine Lions Club pay for No. 8 and agree to restore it.
Local Apex and Rotaract pledge support.
Trolley crane donated by member. |
RSA76-86 |
| 1982 |
November |
Society purchases material to enable track work
repairs and renovation to start. 200 sleepers and hardware; 4 sets of points
and timbers; 30 lengths of rail.
Work commences on shed in Maldon Yard. (Gang shed?) |
RSA76-86 |
| 1982 |
December |
2 "U" Vans purchased from Vic Rail. |
RSA76-86 |
|