MALDON JUNCTION (CASTLEMAINE) TO MUCKLEFORD RESTORATION
-
Track
- Removing old sleepers, November, 2001
- First length of new track, December, 2001
- Newly laid track, 9th June, 2002
- Screw-Dog driver, 9th June, 2002
- Laying track near 83mp, 10th June, 2002
- First day of ballast trains. 27th July, 2002.
- Driving spikes with pneumatic hammer, August, 2002
- Closing the Gap near Farmer's Bridge. 14th Sept, 2002
- Sleeper Train crossing Farmers Bridge. November, 2002
- Laying track, up side of Sawmill Road Crossing. 26th Nov, 2002
- Laying Maldon Jctn / Midland Hwy, 16th Feb, 2003
- F212 on sleeper train at M'ford, 27th Feb, 2003
- Btwn Midland Hwy & Winters Flat, 2nd March, 2003
- Laying track Winter's Flat Bridge, 8th March, 2003
- Ballast Plough, 14th March, 2003
- Track across Winter's Flat Bridge, 15th March, 2003
- Join-Up. 14th June 2003
- Join-Up. Workers Group Photo. 14th June 2003
- Ballast at Maldon Junction 7th July 2003
- Ballast Machines 22nd July 2003
- After tamper & regulator have passed. 22nd July 2003
- VGR Tamper at Pyrenees Hwy Bridge. 16th Aug. 2003
-
Muckleford - Castlemaine Signals & Safeworking
- M'ford Down Home Signal Mast, 4th Sept. 2003
- Midland Hwy Lights, 26th Sept. 2003
- Midland Hwy Crossing (i), 25th Oct. 2003
- Midland Hwy Crossing (ii), 25th Oct. 2003
- C'maine Catch Points signal mast installed, 14 Feb, 2004
- C'maine Catch Points at Up end, 28 Feb, 2004
- C'maine New Arrival signal mast, 28 Feb, 2004
- C'maine New Pull Wires, 1 May, 2004
- C'maine Pull Wires, 1 May, 2004
- Castlemaine Post 8, 22 May 2004
-
Winter's Flat Bridge
- Removing material over Langslow Street. 25th January, 2002
- New piers over Langslow Street. February, 2002
- Only 3 piers to be replaced, 6th February, 2002
- The last pier being positioned, 27th February, 2002.
- Decking progress, April, 2002
- Decking work progress, April, 2002
- View along up side of completed bridge, 19th May, 2002
- View along top of completed bridge, 10th June, 2002
- The Bridge Gang, May, 2002.
-
Pyrenees Highway Bridge
- As at 14th September, 2002
- Removing spans, 18th November, 2002
- Preparing bridge bearings, 27th February, 2003
- Replacing spans, 7th April, 2003
- Decking the bridge, April 2003
-
Rifle Range Bridge
-
Sawmill Road (Prison Farm) Bridge
- Bridge Details.
- 'Up' end of the bridge before work commenced
- Deck removed, March, 2002
- Deck removed, March, 2002
- Pier removal commenced, April, 2002
- Backfilling new pier, 31 May,2002
- New pier is prepared, 31 May,2002
- Towards 'down' end creek bed, 9 June, 2002
- Section of bridge over the creek bed, 6 July, 2002
- Completed bridge from the 'down' side, July, 2002
- Laying track, 5th Oct, 2002
-
Farmers Bridge
- Bridge Details.
- Before restoration, December, 2001
- Before restoration, March, 2002
- First new pier, July, 2002.
- Placing 'up' end pier, 13th July, 2002.
- Final pier in place, 28th July, 2002.
- South Side with track laid. 8th Sept, 2002
- Track laid across bridge, 14th Sept, 2002
- Sleeper Train crossing Farmers Bridge. November, 2002
-
Walmer Road Bridge